Yarra River Services Protection Project

Tuesday, September 3, 2024


Port of Melbourne issues public notices from time to time, advising of changes or activities in and around the port that may impact the industry and/or local community.

Yarra River Services Protection Project

Last updated: 02/09/24

As part of the Channel Deepening Project in 2008-2009, the Yarra River Services Protection Structures were installed as a safeguard over three trunk services in the Yarra River downstream of the West Gate Bridge.

Port of Melbourne will soon be undertaking works including:

  • Visual survey of the grouted rock protection structure to inform defects?; and
  • Remediation of deteriorated grouted rock.

Works are scheduled to commence from week commencing 16 September 2024 and may take between 6-8 months to complete, subject to weather conditions and actual extent of defects. Port of Melbourne has worked closely with Ports Victoria to establish a set of protocols that provide maximum flexibility while facilitating these essential works.

Conformation of works will be issued via Notice to Mariners.

For further information a fact sheet can be downloaded here: Yarra River Services Protection Project Fact Sheet

For further information a fact sheet can be downloaded here: Yarra River Services Protection Project Presentation